In a statement on November 20, 2026, Oracle said it had raised all the rent funding needed to fulfill its deal with OpenAI earlier that month. The company described any further private discussions with suppliers as supplementary options, not funding required for the deal.
Oracle also reported progress on the partners’ AI infrastructure projects. It said the Abilene, Texas, campus had been used to train GPT-6 Astra and was nearly complete. According to Oracle, the next gigawatt-scale project, Shackelford, had received all permits. The company said deliveries of NVIDIA Vera Rubin racks were on schedule and expected to finish within the following few weeks.

Oracle maintained its forecast of positive free cash flow in the second half of fiscal 2028. It is targeting more than $30 billion in free cash flow in fiscal 2029 and expects to fund future growth from its own cash flow from then on.